01244 289944

Hawarden High School

Hawarden High School

In April 2013 MACP won a tender with Flintshire County Council to install a complete new fire alarm system at Hawarden High School .

The project was worth in excess of £147k and successfully completed within the specified 12 month timescale.

MACP were a subcontractor to MPH construction with whom we developed a close working relationship.

This installation was a complex process with the works being carried out during both term times and school holidays.

The feedback from all parties at completion was very positive with MACP subsequently winning a second contract with another high school.

We are currently installing a complete new fire alarm system at Ysgol Maes Garmon and again subcontracting for MPH construction.